Building Timeline in Lake Ridge
Depending on the size of your house, pre-grade lot preparation and other factors, building a custom home in Lake Ridge takes anywhere from 8 months to 1 ½ years.
Below is an estimated timeline of a 2,500 sq ft custom home build:
1 month - Purchasing a lot
2 weeks - Architectural blueprints
1 month - Surveys and tests
3 weeks - City permits & POA approval
1 month - Chemical injections, foundation prep and inspections
5-8 month - From pour of slab until completion
Factors that delay a build timeline:
Mother nature
Subcontractors backlogged
Inspections and corrections
COVID 19
Material backlogged (rare)